It took 21 calendar days to construct the electrical installation of a new Photovoltaic Park in Thesprotia.
The work carried out by our teams included:
- Electrical interconnection of the PV panels
- Installation of grounding systems
- Installation of general AC & DC cabling
- Installation of Medium Voltage general cabling
- Installation of monitoring cabling for central DC Inverters
- Connection of AC & DC cables to the DC Inverters
- Electrical installation of prefabricated shelters
- Connection of DC & AC panels
- Connection of two substations, VLF measurements
- Commissioning and handover of the project